• <tr id='18613'><strong id='3852c'></strong><small id='9bc47'></small><button id='e965c'></button><li id='09882'><noscript id='1a856'><big id='2c9e9'></big><dt id='ad80d'></dt></noscript></li></tr><ol id='95656'><option id='58271'><table id='e3536'><blockquote id='38948'><tbody id='e045d'></tbody></blockquote></table></option></ol><u id='09e24'></u><kbd id='ad259'><kbd id='c3fb0'></kbd></kbd>

    <code id='4b98e'><strong id='0a1ea'></strong></code>

    <fieldset id='edf83'></fieldset>
          <span id='d6489'></span>

              <ins id='82d76'></ins>
              <acronym id='0a201'><em id='23457'></em><td id='a0bc5'><div id='20f03'></div></td></acronym><address id='9aeca'><big id='5d8ba'><big id='598c6'></big><legend id='7ac09'></legend></big></address>

              <i id='78eb1'><div id='31683'><ins id='411c3'></ins></div></i>
              <i id='7221e'></i>
            1. <dl id='cc8bd'></dl>
              1. <blockquote id='29a5b'><q id='432ca'><noscript id='f3020'></noscript><dt id='05dd6'></dt></q></blockquote><noframes id='3a55f'><i id='fd97c'></i>
                当前位置: 首页 > 今日建平 >

                建平高铁站建设工作进入“冲刺阶段”

                (文章来源:建平县) 发布时间:2020-04-23 【 打印此页

                为了完善建平高铁站前区功能,建平县于3月18日启动建平站站前综合服务广场项目建设,目前项目建设进展迅速,“高铁时代”离建平越来越近。


                建平高铁站位于建平县红山街道杨杖子村,是始发于内蒙古通辽的赤喀高铁线路的一个重要经停站,引入喀左县后并入京沈高铁。车站设计规模为2台4线,设侧式站台2座,站中心设旅客地道一座。作为全县未来重要的交通枢纽,建平县将高铁站建设作为城市新名片来打造。


                记者在工程建设现场看到,工程机械正在紧张作业,工作人员正有序铺砖、穿线、测量,忙碌不停,高铁站广场项目进入冲刺阶段。


                据了解,高铁站广场建设项目总占地3万平方米,建设大理石广场、环路、停车场、绿化带等设施。其中,大理石广场面积1.1万平方米;广场环路路面宽14米,面积8700平方米;停车场8100平方米;大理石广场四周建乔木、灌木结合的绿化带,设置路灯12盏,广场中心设置高杆灯一盏,环路两侧建3米宽乔木、灌木结合的绿化带,整个广场绿化面积达到2200平方米。


                据介绍,高铁站广场项目从318号开始施工,现已完成全部场平、土石方工作。正在进行水稳基层施工,下一步将进行火烧板铺设和环路路面施工。全部工程预计在615号前后结束。


                目前,建平高铁站主体已全部完成,内部装饰也在全面完善,现在正处在高铁试运行阶段。按照计划,建平站将于今年7月份正式运行。届时,一座全新的城市高铁站将展现在建平人民面前。高铁站的建成,不仅方便人民群众出行,对建平经济社会的发展也将起到更好的推动作用。